介绍: 森林步道及景观工程的示范段,起于体育公园,市民通过环形坡道进入森林栈道,沿着山势盘旋进入森林步道主线或现状水泥路,该进出口还设步道进入水泥路。示范段总长1274.741米。其他出入口设置栈道或步道接入主线,接入主线部分长123.569米。 2、建设规模 森林步道及景观工程施工,栈道采用钢结构形式架设。工程内容包括森林步道主体工程、步道各出入口、各景观节点、步道配套设施建设、步行道周边山体景观修复及绿化提升、夜景灯光、音频设计备、还建工程等。 项目选址面积40232.4平方米,主轴线连接xx公园,以长度6267米的无障碍架空栈道为主,车行道3000米,登山步道8200米。 目录 第一章 编制依据及范围·····································2 第二章 工程概况···········································3 第三章 施工部署···········································6 第一节 质量、进度、安全目标·······································7 第二节 项目管理总体安排···········································7 第三节 设备、人员动员周期和设备、人员、材料运到施工现场的方法····10 第四节 施工调度···················································10 第四章 施工方案··········································11 第一节 施工准备···················································11 第二节 基础工程施工方案···········································13 第三节 钢桁架工程施工方案·········································20 第四节 给排水工程施工方案·········································31 第五节 电气工程施工方案···········································33 第六节 坡道景观工程施工方案·······································39 第五章 施工进度计划······································50 附 施工进度计划表·············································51 第六章 资源供应计划······································52 第七章 施工平面布置······································57 附 项目部平面布置示意图·······································60 第八章 技术组织措施计划··································61 第一节 保证进度目标的措施·········································61 第二节 保证质量目标的措施·········································66 第三节 分项工程施工质量保证措施···································68 第四节 保证安全目标的措施·········································77 第五节 保证成本目标的措施·········································89 第六节 保证季节施工的措施·········································91 第七节 保证环境的措施·············································94 第八节 文明施工的措施·············································98 第九章 实施难点和对策···································101 第十章 其他应注意的事项·································103